Site · Operational
Vantage CWL1 Newport campus
Coedkernew, Newport, Wales
Established campus operational since 2010. Vantage and Nebius announced high-density NVIDIA AI capacity in August 2026.
- Operator or sponsor
- Vantage Data Centers; Nebius AI deployment
- Published scale
- 148MW critical IT load at full buildout
- Project evidence checked
148 MW is the campus design figure for critical IT load. The operator has not confirmed commissioning of the separate Nebius installation.
AI evidence
AI proposal / commitment · technical evidence incomplete
AI training/inference capacity commitment; technical and operational scope is deployment-specific.
148 MW is the campus design figure for critical IT load. The operator has not confirmed commissioning of the separate Nebius installation.
Planning evidence
Newport City Council · Host authority identified
The CWL1 campus is in Newport, although marketed under a Cardiff location label. This identifies the host council; a building-by-building consent audit has not been completed.
Operator: Newport campus and AI deployment