Site · Proposed
Thames Valley Park data-centre proposal
Earley, near Reading, England
Outline application 262274 registered 28 September 2026 to replace office buildings at the Microsoft campus with a data centre, fuel cells and supporting infrastructure.
- Operator or sponsor
- FH Trustees Limited (applicant); BCS project manager
- Published scale
- 72MW proposed IT load
- Project evidence checked
The promoter describes 72 MW IT load. Wokingham’s current determination was unverified during the November review.
AI evidence
AI scope unverified
72MW IT and fuel-cell proposals describe infrastructure rather than an AI cluster.
The promoter describes 72 MW IT load. Wokingham’s current determination was unverified during the November review.
Planning evidence
Wokingham Borough Council · Application record located
Application 262274 is on Wokingham’s register. A Reading-area address does not make Reading Borough Council the decision authority.
Council: application 262274