Proposed four-building development on former clay workings. The June 2026 Section 35 direction requires a Development Consent Order. The developer states a signed grid connection for October 2034.

Operator or sponsor
Quest Pit Limited / Questpit Limited
Published scale
Up to 720 MW IT load; up to 1 GW total campus demand in application material
Project evidence checked

The 2034 date is for a grid connection. Earlier permission for film studios is separate. No opening date or data-centre consent verified.

AI evidence

Mixed / broader infrastructure · AI predominance unverified

Grid/private-wire proposals support supply strategy, not installed AI compute.

The 2034 date is for a grid connection. Earlier permission for film studios is separate. No opening date or data-centre consent verified.

Planning evidence

Central Bedfordshire Council · Section 35 direction verified

The June 2026 direction places the data-centre proposal in the national route. Central Bedfordshire is the host authority, despite the Bedford address. A direction is not a Development Consent Order.

Government: Questpit Section 35 direction