Site · Delayed

Nscale Loughton AI campus

Loughton, Essex, England

Nscale says the local power provider withdrew the scheduled connection and power allocation, leading to termination of the Loughton Microsoft agreement. The original plan targeted Q1 2027.

Operator or sponsor
Nscale · Microsoft withdrew as anchor customer
Published scale
Original plan: 23,040 NVIDIA GB300 GPUs; 50MW AI capacity, scalable power allocation up to 90MW
Project evidence checked

Nscale says it is exploring alternative power. A replacement customer, power agreement and opening date remain unverified.

AI evidence

Documented AI design · live service unverified

50MW AI/HPC plan, scalable power allocation and liquid-cooling design are documented.

Nscale says it is exploring alternative power. A replacement customer, power agreement and opening date remain unverified.

Planning evidence

Epping Forest District Council · Council involvement evidenced

District council material references the Loughton proposal. Loughton Town Council can represent local views but is not the district planning decision-maker. The full consent history is not audited here.

Council: Loughton Nscale discussion