Site · Delayed
Nscale Loughton AI campus
Loughton, Essex, England
Nscale says the local power provider withdrew the scheduled connection and power allocation, leading to termination of the Loughton Microsoft agreement. The original plan targeted Q1 2027.
- Operator or sponsor
- Nscale · Microsoft withdrew as anchor customer
- Published scale
- Original plan: 23,040 NVIDIA GB300 GPUs; 50MW AI capacity, scalable power allocation up to 90MW
- Project evidence checked
Nscale says it is exploring alternative power. A replacement customer, power agreement and opening date remain unverified.
AI evidence
Documented AI design · live service unverified
50MW AI/HPC plan, scalable power allocation and liquid-cooling design are documented.
Nscale says it is exploring alternative power. A replacement customer, power agreement and opening date remain unverified.
Planning evidence
Epping Forest District Council · Council involvement evidenced
District council material references the Loughton proposal. Loughton Town Council can represent local views but is not the district planning decision-maker. The full consent history is not audited here.
Council: Loughton Nscale discussionSources
- Nscale: amended SEC filing, 12 November 2026
- Nscale: Loughton design and capacity
- Nscale: original UK deployment announcement (16 September 2025)
- DCD: Microsoft withdraws; Nscale still pursuing Loughton
- AFP: Microsoft confirms withdrawal from Loughton (via Yahoo)
- Reuters: Microsoft ends Loughton agreement (via Investing.com)
- Euronews: reported grid delay