Site · Proposed
Apatura Wester Hermiston
Wester Hermiston, Edinburgh, Scotland
Apatura proposes a 200 MW campus. Scottish ministers determined on 17 August 2026 that an environmental impact assessment is required.
- Operator or sponsor
- Apatura
- Published scale
- 200MW proposed campus
- Project evidence checked
Current consultation describes proposed development; no grant of planning consent established from the cited source.
AI evidence
AI proposal / commitment · technical evidence incomplete
Campus sustainability/power proposals do not settle an AI system design.
Not an equipped AI facility.
Planning evidence
City of Edinburgh Council · Environmental impact assessment required
Ministers decided case EIA-230-002, corresponding to council screening reference 25/05576/SCR. The council records pre-application notice 25/03978/PAN.
Scottish Government: Wester Hermiston screening decision